The permit application fee is based upon the proposed area of disturbance, in square feet.
The following tables illustrate the fee structure:
| Fee schedule for projects NOT in the Protected Shoreland | ||
|---|---|---|
| Area of disturbance in square feet (sf) | Fee | |
| < 100,000 | $250 + $0.005 per sf | |
| 100,000 to 199,999 | $1,250 | |
| 200,000 to 299,999 | $1,750 | |
| 300,000 to 399,999 | $2,250 | |
| 400,000 to 499,999 | $2,750 | |
| 500,000 to 599,999 | $3,250 | |
| 600,000 to 699,999 | $3,750 | |
| 700,000 to 799,999 | $4,250 | |
| 800,000 to 899,999 | $4,750 | |
| 900,000 to 999,999 | $5,250 | |
| 1,000,000 to 1,099,999 | $5,750 | |
| (Table continues at $500 per additional 100K sf of disturbance) | ||
| Fee schedule for projects IN the Protected Shoreland | ||
| Area of disturbance in square feet (sf) | Fee | |
| < 50,000 | $250 + $0.005 per sf | |
| 50,000 to 199,999 | $1,250 | |
| 200,000 to 299,999 | $1,750 | |
| 300,000 to 399,999 | $2,250 | |
| 400,000 to 499,999 | $2,750 | |
| 500,000 to 599,999 | $3,250 | |
| 600,000 to 699,999 | $3,750 | |
| 700,000 to 799,999 | $4,250 | |
| 800,000 to 899,999 | $4,750 | |
| 900,000 to 999,999 | $5,250 | |
| 1,000,000 to 1,099,999 | $5,750 | |
| (Table continues at $500 per additional 100K sf of disturbance) | ||
Please make checks payable to: "Treasurer State of New Hampshire."